Nigerian govt announces fresh repair of Third Mainland Bridge

The Federal Controller of Works in Lagos, Mr Adedamola Kuti, has said that traffic arrangements were ongoing to begin another phase of major repair on the Third Mainland Bridge.

Kuti told the (NAN) in Lagos that results of investigative tests on the bridge were ready and that contractors would move to site at the completion of the traffic management architecture.

“Any moment from now, once I get our traffic plans approved, we may be announcing to the world again that we are now ready to fix Third Mainland Bridge based on investigative tests we had last year.

“Meanwhile, we have already completed the resurfacing, the markings, such that you can now drive on Third Mainland bridge smoothly.

“We are also going to repair some of the piles or pillars carrying the bridge; that is the next phase that we are doing; so work will soon begin on Third Mainland Bridge,’’ he said.

Kuti said that the Muhammadu Buhari administration was committed to fixing bridges in Lagos.

He said that this was evident in the number of bridges that had been repaired the state, with many more receiving attention.

“This government has very good plans for bridges. Since I came on board, about a year ago, we have completed maintenance and repair works on Leventis Bridge damaged by fire in 2016 where a whole deck collapsed.

“We have also completely repaired the Ijora-7Up Bridge; Coconut Bridge repair has been completed, the burnt Marine Beach Bridge repair has been completed and, as I speak, maintenance work is ongoing on the Independence Bridge on the Island.

“Work is ongoing on the Dorman Long Bridge, you can drive smoothly on it now and all the guard rails and expansion joints are being replaced.

“Work is ongoing on the Ojuelegba Bridge as well as Alaka Bridge,’’ he told NAN.

According to him, although procurement issues affected project delivery, there are enough materials from Alaka Bridge expansion joint works to repair adjoining bridges on the Apapa-Ijora axis.

The controller said he had given instruction to a contractor to move to site to rehabilitate a portion of the Apapa Bridge. (NAN)



No comments:

Disclaimer
Most News articles reported on LOCAL AFRICAN REALITY are a reflection of what is published in the media. LOCAL AFRICAN REALITY is not in a position to verify the accuracy of daily news articles, however, we ensure that only news articles from credible sources are reflected in this service. Independent opinions which are mailed to us may also be published from time to time at our discretion, however the sources for these independent articles will be clearly stated.


Share your story with us: SMS: +23409067561649, Whatsapp: +2349067561649, Email: localafricanreality@gmail.com or qubesentertainmentmagazine@yahoo.com
Receive Alerts on: Whatsapp: +2349067561649, Twitter: @localafricanr